Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 KOILAKUNTLA 5 4.88 7.89 6.29 80.00
2 KOLIMIGUNDLA 16 4.89 21.87 11.01 56.25
3 OWK 6 4.89 6.89 6.22 100.00
Total 27 4.88 21.87 9.07 70.37