Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ALLAGADDA 9 1.88 6.9 4.99 100.00
2 KOILAKUNTLA 27 4.88 21.87 9.07 70.37
3 NANDYAL RURALS 27 0.89 58.89 10.81 74.07
4 NANDYAL TOWN 120 0.87 17.89 6.57 84.17
Total 337 0.89 26.89 7.24 85.16