Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 NANDYAL_DIST1 4 2.84 34.17 17.74 25.00
2 NANDYAL_DIST2 9 3.36 6.79 5.87 100.00
3 NANDYAL_DIST3 7 1.89 14.63 6.16 85.71
Total 20 1.89 34.17 8.35 80.00