Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ALLAGADDA 4 2.84 21.99 8.43 75.00
2 CHAGALAMARRY 1 116.38 116.38 116.38 0.00
3 SIRIVELLA 6 5.23 9.29 6.55 83.33
Total 11 2.84 116.38 17.22 72.73