# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ALLAGADDA 31 0.7 13.79 6.49 54.84
2 KOILAKUNTLA 16 0.62 21.62 7.66 81.25
3 NANDYAL RURALS 119 2.95 25.62 8.33 86.55
4 NANDYAL TOWN 140 0.79 72.79 6.89 96.43
Total 448 0.91 26.95 7.77 84.15