Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 NANDIKOTKUR RURALS 8 4.9 25.88 11.26 50.00
2 NANDIKOTKUR TOWN 11 2.88 42.88 16.34 45.45
Total 19 2.88 42.88 14.2 47.37