Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 KALLUR 8 0.62 20.63 9.32 62.50
2 KURNOOL RURALS 5 4.85 31.53 13.56 40.00
3 ORVAKAL 1 5.15 5.15 5.15 100.00
Total 9 4.87 11.28 6.4 88.89