# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 KURNOOL 23 3.0 8.0 5.61 95.65
2 KURNOOL OPERATION 4 9.0 14.0 11.75 0.00
3 KURNOOL-II 10 3.0 13.0 6.5 70.00
Total 37 3.0 14.0 6.51 78.38