Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BANGANAPALLI 16 4.85 32.93 14.86 6.25
2 BETHAMCHERLA 7 4.88 16.94 7.76 71.43
3 DHONE 21 5.15 46.04 11.53 23.81
Total 44 4.85 46.04 12.14 25.00