Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BETAMCHERLA RURAL 7 5.88 17.88 10.6 42.86
2 BETAMCHERLA TOWN 3 4.89 17.89 9.89 66.67
Total 10 4.89 17.89 10.39 50.00