Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BANAGANPALLY 12 2.88 18.88 10.72 41.67
2 BETAMCERLA 10 4.89 17.89 10.39 50.00
3 DHONE 52 1.89 20.88 9.88 46.15
Total 74 1.89 20.88 10.09 45.95