# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 DHONERURAL 1 6.44 6.44 6.44 100.00
2 DHONETOWN 8 2.95 11.05 6.66 75.00
3 JALADURGAM 1 6.79 6.79 6.79 100.00
4 PEAPULLY 1 3.65 3.65 3.65 100.00
5 VELDURTHY 5 4.83 6.51 5.6 100.00
Total 16 2.95 11.05 6.14 87.50