Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 B.PALLI (R) 4 8.33 14.54 11.09 0.00
2 B.PALLI (U) 1 4.9 4.9 4.9 100.00
Total 5 4.9 14.54 9.85 20.00