# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BANGANAPALLI 5 4.9 14.54 9.85 20.00
2 BETHAMCHERLA 11 1.47 12.8 6.54 81.82
3 DHONE 35 0.66 14.25 4.35 85.71
Total 51 0.66 14.54 5.36 78.43