Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 AE DEVANAKONDA 4 7.7 10.98 9.9 0.00
2 MADDIKERA 3 7.93 11.99 9.31 0.00
3 TUGGALI 1 10.02 10.02 10.02 0.00
Total 12 4.35 13.93 6.57 83.33