Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 KOSIGI 1 12.93 12.93 12.93 0.00
2 MANTRALAYAM 2 9.02 13.97 11.5 0.00
Total 12 4.35 13.93 6.57 83.33