Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 AE ALLUR 1 5.13 5.13 5.13 100.00
2 AE ASPARI 2 5.72 9.93 7.83 50.00
3 AE HOLAGUNDA 1 6.12 6.12 6.12 100.00
4 HALAHARVI 3 7.86 11.95 9.26 0.00
Total 12 4.35 13.93 6.57 83.33