Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ADONI RURALS 5 4.89 7.88 6.29 80.00
2 ADONI TOWN 1 13 3.88 43.88 9.12 92.31
3 ADONI TOWN 2 3 5.88 25.88 18.55 33.33
4 ADONI TOWN 3 3 3.9 14.9 11.23 33.33
5 KOWTHALAM 6 4.89 19.88 10.55 33.33
Total 30 3.88 43.88 10.09 66.67