Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ADONI 30 3.88 43.88 10.09 66.67
2 ALUR 4 4.87 93.9 27.64 75.00
3 MANTRALAYAM 10 4.87 56.89 16.98 50.00
4 PATHIKONDA 6 4.88 6.9 6.55 100.00
5 YEMMIGANUR 15 4.88 47.87 12.42 53.33
Total 65 3.88 93.9 12.44 64.62