Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ADONI 4 5.0 16.0 9.5 50.00
2 ALLUR 1 6.0 6.0 6.0 100.00
3 PATTIKONDA 1 13.0 13.0 13.0 0.00
4 YEMMIGANUR 7 5.0 14.0 8.0 71.43
Total 13 5.0 16.0 8.69 61.54