Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 LAKKIREDDY PALLI 12 4.34 13.47 7.09 75.00
2 RAYACHOTY 21 4.52 15.3 7.03 85.71
3 RAYACHOTY RURALS 16 4.38 15.55 7.38 75.00
Total 30 4.1 17.5 6.99 76.67