Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL January-2022 To March-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 L R PALLI 19 5.96 26.7 9.44 84.21
2 RAYACHOTY 71 2.62 26.94 9.12 69.01
3 RAYACHOTY RURAL 25 2.62 21.95 8.8 80.00
Total 210 1.94 26.95 8.22 83.81