Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 KODUR 5 6.52 32.02 14.49 20.00
2 RAJAMPET 2 6.44 6.71 6.58 100.00
Total 67 0.61 44.02 7.92 82.09