Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 NANDALUR 2 4.34 5.26 4.8 100.00
2 SIDHAVATTAM 3 5.16 16.86 9.22 66.67
3 VONTIMITTA 5 4.81 16.82 7.48 80.00
Total 23 2.69 15.93 6.63 78.26