Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 PULIVENDULA 17 4.57 18.65 7.28 76.47
2 PULIVENDULA(RURALS) 2 4.91 6.95 5.93 100.00
3 VEMPALLI 4 4.96 6.35 5.81 100.00
Total 44 0.16 31.78 9.59 68.18