Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL January-2022 To March-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 PULIV RURALS 16 3.91 89.95 15.3 75.00
2 PULIVENDULA 30 2.95 62.94 9.81 86.67
3 VEMPALLI 44 1.7 47.91 8.77 79.55
Total 210 1.94 26.95 8.22 83.81