Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 JAMMALAMADUGU 8 0.16 61.03 11.86 87.50
2 PRODDATUR 23 0.16 11.65 5.61 86.96
3 PRODDATUR RURALS 9 0.16 19.04 5.08 88.89
4 YERRAGUNTLA 19 0.16 23.3 6.38 89.47
Total 44 0.16 31.78 9.59 68.18