Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 JAMMALAMADUGU 9 2.07 12.13 7.59 66.67
2 PRODDATUR 18 1.9 16.76 8.28 50.00
3 PRODDATUR RURALS 10 2.1 11.04 6.58 60.00
4 YERRAGUNTLA 12 1.84 16.2 7.0 75.00
Total 30 4.1 17.5 6.99 76.67