Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BADVEL 30 4.87 6.9 6.19 100.00
2 MYDUKUR 48 2.87 17.88 7.0 87.50
3 PORUMAMILLA 2 5.89 6.9 6.39 100.00
Total 150 1.88 43.89 8.2 86.67