Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL Oct-2020 To Dec-2020
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BADVEL 2 0.0 0.0 0.0 100.00
2 MYDUKUR 5 0.0 0.0 0.0 100.00
Total 3 0.0 0.0 0.0 100.00