Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 KADAPA OCC1 19 0.61 44.02 9.01 73.68
2 KADAPA OCC2 17 3.45 16.84 6.84 88.24
3 KADAPA OPERATION 1 1 28.99 28.99 28.99 0.00
4 KADAPA OPERATION 2 30 3.01 30.93 7.15 86.67
Total 67 0.61 44.02 7.92 82.09