Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BALAJI NAGAR 4 4.88 6.88 5.63 100.00
2 KADAPA SOUTH 6 4.88 34.89 10.71 83.33
3 KADAPA WEST 10 5.87 20.89 12.58 40.00
4 SAIPET 2 5.85 6.88 6.37 100.00
Total 22 4.88 34.89 10.24 68.18