Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHENNUR 8 4.65 9.04 6.15 87.50
2 VALLUR 1 5.84 5.84 5.84 100.00
Total 0 0.0 0.0 0.0 0.00