Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ANANTHAPUR 119 3.01 71.82 8.27 80.67
2 ANANTHAPUR RURAL 19 3.01 28.04 8.38 73.68
3 GOOTY 56 3.38 44.85 7.46 87.50
4 HINDUPUR 101 0.68 29.93 6.53 83.17
5 KADIRI 21 3.01 14.75 6.78 76.19
6 KALYANDURG 13 4.83 90.02 13.89 76.92
Total 329 0.68 90.02 7.73 81.76