Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ANANTHAPUR 284 0.88 25.88 6.81 89.79
2 GOOTY 59 0.86 35.89 8.99 76.27
3 HINDUPUR 230 0.89 34.88 7.72 77.39
4 KADIRI 75 2.89 38.88 9.5 70.67
5 KALYANDURG 48 1.87 65.88 12.07 64.58
Total 696 0.86 65.88 7.95 80.75