Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 KALYANDURG HQ 6 3.95 31.53 13.68 50.00
2 KALYANDURG RURALS 5 5.42 15.64 7.89 80.00
3 RAYADURG 3 4.85 6.03 5.56 100.00
4 URAVAKONDA 2 9.63 23.31 16.47 0.00
Total 125 1.65 27.47 7.08 84.00