Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 KADIRI TOWN 7 3.01 11.95 6.14 85.71
2 KADIRIEAST 1 5.99 5.99 5.99 100.00
3 KADIRIWEST(R) 5 3.45 6.51 5.6 100.00
4 PUTTAPARTHY 8 4.87 14.75 8.17 50.00
Total 119 3.01 71.82 8.27 80.67