Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 AMADAGURU 5 4.9 22.88 9.28 80.00
2 NALLAMADA 2 5.88 6.89 6.38 100.00
3 O D CHERUVU 5 3.9 38.88 12.69 80.00
4 TANAKALLU 5 6.88 27.87 16.48 40.00
Total 19 2.89 17.89 8.46 52.63