Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHILAMATTUR 10 4.88 6.89 6.29 100.00
2 LEPAKSHI 22 4.9 21.9 9.61 63.64
3 PARIGI 25 4.87 15.88 7.36 84.00
Total 89 0.89 20.89 7.31 76.40