Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 HINDUPUR 61 0.66 18.36 5.72 86.89
2 HINDUPUR RURALS 15 3.96 34.22 12.74 66.67
3 MADAKASIRA 15 4.57 8.7 5.99 93.33
4 PENUKONDA 14 4.35 34.47 9.51 71.43
Total 125 1.65 27.47 7.08 84.00