# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 GOOTY 4 4.75 6.64 5.88 100.00
2 GUNTAKAL 14 3.38 16.97 8.57 71.43
3 TADIPATRI 38 3.96 44.85 7.21 92.11
Total 119 3.01 71.82 8.27 80.67