Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ANANTHAPUR(W) 3 4.35 13.97 8.23 66.67
2 C.K.PALLI 2 6.03 10.94 8.48 50.00
3 DHARMAVARAM 14 3.01 28.04 8.4 78.57
Total 119 3.01 71.82 8.27 80.67