Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ANANTHAPUR(W) 7 6.12 22.63 12.98 28.57
2 C.K.PALLI 5 5.73 26.68 12.05 60.00
3 DHARMAVARAM 45 2.9 32.74 11.13 60.00
Total 125 1.65 27.47 7.08 84.00