Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ANANTAPUR-II 89 3.38 27.47 6.2 94.38
2 ANANTHAPUR 15 1.65 20.24 7.75 66.67
3 ANANTHAPUR(E) 21 4.85 20.99 10.31 52.38
Total 125 1.65 27.47 7.08 84.00