Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL January-2022 To March-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ANANTHAPUR EAST 57 5.83 26.91 8.2 89.47
2 ANANTHAPUR TOWN 1 19 5.7 22.94 8.43 89.47
3 ANANTHAPUR TOWN 2 22 0.96 24.83 9.31 81.82
4 ANANTHAPUR WEST 61 5.79 25.91 8.78 80.33
5 DHARMAVARAM 92 0.94 67.94 8.73 89.13
Total 251 0.94 67.94 8.65 86.45