Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 33kV October-2021 To December-2021
# Circle Number of Applications 33kV Min Duration(Days)33kv Max Duration(Days)33kv Average Duration(Days)33kv Applications Processed(%) 33kV
1 KURNOOL 2 27.9 29.88 28.89 100.00
2 TIRUPATI 1 24.88 24.88 24.88 100.00