Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 33kV October-2021 To December-2021
# Division Number of Applications 33kV Min Duration(Days)33kv Max Duration(Days)33kv Average Duration(Days)33kv Applications Processed(%) 33kV
1 DHONE 1 27.9 27.9 27.9 100.00
2 KURNOOL 1 29.88 29.88 29.88 100.00
Total 2 27.9 29.88 28.89 100.00