Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV April-2022 To June-2022
# Circle Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 ANANTHAPUR 14 3.91 14.66 9.97 100.00
2 KADAPA 8 11.66 42.87 20.34 75.00
3 KURNOOL 6 12.75 14.91 14.14 100.00
4 NELLORE 20 5.91 66.75 23.15 60.00
5 TIRUPATI 8 9.79 11.61 10.88 100.00
Total 56 3.91 66.75 16.74 82.14