Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2021 To September-2021
# Sub-Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 TIRUPATI OPERATION1 1 14.62 14.62 14.62 100.00
2 TIRUPATI OPERATION2 1 14.76 14.76 14.76 100.00
Total 2 14.62 14.76 14.69 100.00