Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2021 To December-2021
# Sub-Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 NAGALAPURAM 2 12.87 15.88 14.38 50.00
2 PUTTUR 1 24.89 24.89 24.89 0.00
Total 3 12.87 24.89 17.88 33.33